Albyn School Redevelopment Project

Development Webcam 2 Development Webcam 2 Craig Group HSBC Robertson McLeod + Aitken

January 23 2012

   

 

 January 17 2012

The front entrance has made some good progress over the last few weeks with the glass being installed at the weekend. Over the next week there should be some significant activity and we should start to see the wonderful new entrance to Albyn School.

   

 

December 16 December 2011
Below are some updated photos of the front entrance including the new first floor which will be open to the pupils for the new year.

 

 

 November 16 2011
The front entrance at Albyn School is making steady progress, the glass is expected in the next few weeks and we should start to see the brand new face of Albyn School. The classrooms in the new classroom block are taking shape and is all on schedule.

 

October 13 2011

DSC07740DSC07750DSC07747DSC07758DSC07760DSC07736 DSC07718DSC07713DSC07729 DSC07719

September 22 2011

On Thursday 22 September 2011, Councillor Jill Wisely officially opened the new Albyn School Nurseries and Science Laboratories. The ceremony marked the end of the first phase of the redevelopment project, one of the most significant periods of development in the school’s 144 year history. The Chairman of the Governors, Headmaster, Senior Management team and science and nursery staff were also  joined by representatives from the companies who are involved with the project; Archial, HFM, McLeod and Aitken, Robertson and Wallace Whittle.

 047  065 067 095 110 113

September 19 2011

Front Entrance

DSC07652 DSC07651

Classroom Block

DSC07626 DSC07647

DSC07624 DSC07644

Links

DSC07653 DSC07655

 

 

New Nurseries Open week commencing 12 September

DSC07613DSC07612

DSC07603 DSC07610

 

September 2 2011

DSC07556 DSC07512

August 26 2011
DSC07506 DSC07478

DSC07504 DSC07475

August 19 2011
The new term is about to commence and the first phase of the building project is now complete. There are now 3 new science labs ready for the start of term. The new links are nearing completion and the new toddler nursery will be finished in a few weeks time. One of the more visible aspects of the project over the summer has been the demolishing of the existing front entrance. In the next few weeks scaffolding will be erected and construction will begin on a new front entrance. In the playground a steel structure has begun to take shape and will eventually become the new classroom block.

DSC07282 DSC07342DSC07307 DSC07334DSC07332DSC07335 DSC07347DSC07336

August 11 2011

DSC07276 DSC07260

DSC07266 DSC07282

DSC07270 DSC07263

DSC07272 DSC07271

August 5 2011

DSC07240 DSC07231
DSC07225 DSC07254
 
DSC07213 DSC07249
DSC07244

July 21 2011

DSC07033 DSC07034

DSC07046 DSC07066

DSC07071 DSC07072 DSC07074

July 15 2011

DSC06973 DSC06970

DSC07000 DSC06982

DSC06989 DSC06968

 

July 13 2011

DSC06881DSC06958DSC06928 DSC06955

DSC06874DSC06950
DSC06916 DSC06899

July 4 2011

DSC06802 DSC06764

DSC06796DSC06749

June 28 2011

DSC06707DSC06714 DSC06723 DSC06730 DSC06738 DSC06737

June 24 2011
This week at Albyn there has been a lot of developments on the building site. Preparations are underway for the demolition of the existing front entrance and links between no 17-19 and 19-21 due to take place next week. The piling for the new Upper School block will also begin next week.

DSC06676 DSC06681

DSC06684 DSC06692 DSC06687

June 17 2011

DSC06668 DSC06671

June 14 2011
 Mid week update
The science labs have now taken shape with the roof being completed and plasterboard going up in each of the new labs. The new Harriet House nursery is making better progress this week as seen below.

DSC06647DSC06648

DSC06652DSC06658

June 10 2011

DSC06632 DSC06625

DSC06643DSC06636

June 8 2011

Mid-week update

 

DSC06620 DSC06619

June 3 2011

This week work on the science labs has progressed very quickly, the timber kits are now up along with the windows. Next week internal works will begin. On the new Harriet House, the foundations have been laid, block work has begun and the steelwork will be going up this weekend.

DSC06591 DSC06595
 

DSC06604 DSC06607

June 1 2011

Mid-week update!

DSC06577 DSC06582

DSC06587DSC06584

May 27 2011

Here’s some photos from the progress this week.

DSC06564DSC06568

DSC06555DSC06546

 

May 20 2011
This week the brick work under the Oliver Wing was completed and the staffrooom will be demolished within the next few days. Roof work on the labs is on going as is the laying of foundations.
DSC06495DSC06501

May 13 2011
This week work momentarily ceased on the building site with the Foundation Stone laying ceremony on Thursday 12 May 2011. Professor Celso Grebogi was the guest of honour with the school Governors, science staff, the senior management team and representatives from Robertson Eastern (our main building contractor), Archial (architect), McLeod and Aitken (quantity surveyors) and our project manager Mr Gordon Milne all in attendance.

After a successful ceremony work continued on casting the floors in the science labs and garage. The roof structure of the science labs is being constructed and in the Oliver Wing excavations have continued with a focus on the service distributions. In the next week we expect that the existing staffroom of the Oliver Wing will be demolished.

DSC06478 28DSC06492

DSC06485 DSC06480

May 6 2011
This week the concrete has been laid for the foundations for the labs, in the Oliver Wing excavations have been taking place to prepare the foundations. A new fence will be up next week as work will commence on the existing staff room of the Oliver Wing.

DSC06471 DSC06474

April 28 2011
This week the progress on the new labs continued as well as the preparations for the new Harriet House nursery. The builders have been working on the roof for the labs as well as the initial brick work and have taken down further walls inside the existing garages. The foundations for the new Harriet House are being prepared, as is the new staff area for the nursery staff. Let’s hope the good weather continues!

DSC06440DSC06450DSC06455

April 21 2011
This week partitions have been placed between the existing science labs and the Oliver Wing nursery. All pupils have been advised to use the alternative gate to access the labs. The new fire exit in the ante pre-school is working well with the children enjoying the new access to the play area.

DSC06345 DSC06348 DSC06350

April 14 2011

Over the Easter holidays the builders have made noticeable progress on the science labs and new nursery. Work has continued on the construction of new science laboratories with foundations laid and steel being delivered to site to create a new roof structure. Work has also just begun on clearing the area behind the former janitor’s house in preparation for the new Harriet House nursery adjacent to the Oliver Wing. An additional fire exit has been created in the ante-pre school to provide an emergency means of escape into the Oliver Wing garden once the rear entrance of the Oliver Wing is closed off.

DSC06317 DSC06316

April 1 2011
This week work continued on preparing the ground for the laying of the foundations of the labs which will begin soon. In addition, next week the builders will begin putting up fencing around the garden beside the Oliver Wing and the existing science labs and their portakabins will arrive on site.

DSC06259 DSC06261

March 25 2011
This week the back wall between the environmental garden and the new laborotories was removed and work continued on preparing the ground for the laying of the foundations which will take place next week.

DSC06151 DSC06153

March 18 2011
This week work continued on fully removing the wall between the Harriet House garden and the science labs. The ground is being prepared for laying the foundations for the 3 new science labs  in the next few weeks.

DSC06099 DSC06102

 

March 7 2011
The Albyn School Redevelopment Project finally began this week with the contractors, Robertson, taking possession of the site behind Harriet House. A high fence has now been put up to segregate the builders’ compound from the rest of the School and behind this the builders have been getting to work. The tree in the garden of Harriet House has been removed but will be replaced with two new trees at the end of the project. A cross section of the tree trunk has been kept for educational purposes by the nurseries. Work has also begun on the disused garages which will become the new science labs.